Third Avenue reopens as construction completes for the year

Published on November 25, 2026

3rd ave open map

Phase 1 of the Third Avenue project is complete, and the road will be reopening to through traffic between N. Riverfront Drive and Cleveland Street by the end of day Wednesday, November 25. Motorists should be aware that separate natural gas work is still underway between the railroad tracks and Highway 14. This work will result in lane restrictions in the area for the next couple of weeks. Phase 2 of the project is scheduled to begin in spring 2027. Work will take place between the railroad tracks north of Pine Street and Cleveland Street, requiring a full road closure through fall 2027 to accommodate road and utility reconstruction.