Kern Bridge

  • Project typeConstruction Projects
  • Project value$10,516,004
  • Contractor nameRedstone Construction, LLC

The historic Kern Bridge is a bowstring arch bridge that has been removed from its original location over the Le Sueur River in South Bend Township and will be rehabilitated/re-erected to a new location crossing over the Blue Earth River. The location will connect Sibley Park and Land of Memories Park and serve as part of the Minnesota River Trail. This connection and companion trail project in Land of Memories Park will create a continuous trail system from Minneopa State Park to the City of Faribault.

 

Thursday, October 29, 2026

The ribbon cutting was held 10-27. Upcoming is enjoy the new bike trail!

 

Thursday, October 22, 2026

The painting crew was on site finishing painting the piers. The railings across the span are complete.

 

Friday, October 16, 2026

Final lift of bituminous pavement has been placed on both sides of river. Flower bed has been installed adjacent to Sibley Parkway. 70% of the railing has been installed. Road signage has been installed.

Upcoming work includes finish painting the piers. Finish installing the railing. Crosswalk painting.

Ribbon cutting celebrating the completion of the project is scheduled for Tuesday, October 27th at 1:00 pm on the Sibley Park side of the bridge.

 

Thursday, October 8, 2026

     Ongoing work on the railing installation.  The base course of pavement has been placed on Sibley Parkway and the service road on the Land of Memories side.  Trail connections have been paved on both sides of the river.  Black dirt has been placed on the Sibley Park side.

     Upcoming work will include turf restoration, conclusion of the railing system, and the final lift of bituminous.

 

Thursday, October 1, 2026

Railings were installed on the approaches to the bridge on both sides of the river. Fine grading of Sibley Parkway and adjacent trails is occurring. Curb, apron and pedestrian ramps were installed at the bottom of the hill of CHS Pergola Way.

Upcoming work will be pavement on Sibley Parkway and adjacent trails, and the same on the Land of Memories side. 

 