Veterans Memorial Bridge and Hwy 169/Belgrade Interchange

  • Project typeConstruction Projects
  • Project value$21,300,000

The project is led by MnDOT and will be built in coordination with the City of North Mankato's Belgrade Ave. reconstruction project.

Summary of work: Replace the deck of Veteran's Memorial Bridge, which spans over the Minnesota River, the railroad, and Riverfront Dr. Repair approach panels and joints on the bridge over Hwy 169. Replace the signals at the interchange of Hwy 169 and Belgrade Ave. Replace pedestrian ramps and sidewalk to meet Americans with Disabilities (ADA) standards. Provide dual left turn lanes to the Hwy 169 southbound on-ramp. Improve roadway drainage

Traffic impacts: Traffic will be detoured during construction into late fall 2026, weather permitting. Final completion is expected in early summer 2027 with remaining work completed under traffic without additional detours.

View complete information: https://www.dot.state.mn.us/d7/projects/vetsbridge/index.html

Grant: Grant Agreement No. 1061718, State of Minnesota Local Bridge Replacement Program, SP 137-152-002 Veteran’s Memorial Bridge and Hwy 169/Belgrade Interchange Project

Agency Leadership: Susan MH Arntz, City Manager, 507-387-8695

Grant Manager: Cory Bienfang, City Engineer, 507-387-8643

Friday, November 13, 2026

No activity on site this week.

 

Friday, October 30, 2026

Ribbon cutting for the bridge project was held on Friday, October 30th at 2 pm. Bridge is expected to open up for traffic on Saturday, October 31st in the afternoon. Please keep in mind the only the north sidewalk of the bridge will be open to pedestrian traffic until the permanent railing is installed.

 

Thursday, October 29, 2026

Final layer of asphalt pavement has been installed on Mulberry Street adjacent to the east end of the bridge. Expect striping work to occur by the end of the week of 10/26 on Mulberry Street between the east extents of the bridge to N. Broad Street.

 

Friday, October 16, 2026

The majority of the work that is taking place currently is on the North Mankato/TH169 side of the bridge. Paint system is being applied to Span 4. Lighting system/Signal work, concrete paving, and concrete curb and gutter work is taking place on the North Mankato/TH169 side of the bridge.

 

Friday, October 9, 2026

Painting of bridge girder and barrier wall is complete on the bridge span adjacent to the Blue Earth County Library and Bridge Plaza. Painting of bridge girder and barrier wall is on going on span over the railroad tracks. Concrete staircase construction ongoing on the north and south sides of the bridge on the Mankato side adjacent to the Blue Earth County Library and Bridge Plaza.

 

Friday, October 2, 2026

New lighting service cabinet for the City of Mankato street lights is in the process of getting installed. Concrete staircases on the north and south sides of the bridge adjacent to Bridge Plaza and the BEC Library are currently getting constructed.Painting of bridge girders and barrier wall in process on bridge adjacent to Bridge Plaza and BEC Library at the east extents of the bridge.

 

 