Commercial Plan Review Requirements

To facilitate a building project and the city’s permit process, submittals for building permits must be complete at time of application. Permitting time will depend on project complexity, completeness of plan submittals and number of already received project submittals. If needed, a pre-design process is provided and a preliminary meeting will be scheduled to answer questions and assist in the application process.
Commercial plan submittals must include the following:
- One full-size scaled set
- One 11”x17” plan set.
- One electronic set of plans, specifications, and other submittal documents including the building permit application form (Email, jump drive, CD ROM, Dropbox, other pre-approved format)
Plans, documents and specifications must be prepared in accordance with Minnesota statute 326 and Minnesota rules 1800 and 1805.
- Completed and signed city of Mankato permit application
- Soils analysis/geotechnical report by soils engineer
- Land survey (survey requirements handout)
- Civil plans (grading, drainage, utilities, erosion plan)
- Landscape plan (section 10.88 of city code)
- Exterior lighting plan (section 10.89 of city code)
- Building elevations (including materials and colors)
- Floor plans
- Architectural building plans with code analysis, alternate methods, and fire protection
- Structural plans with structural analysis and design calculations
- Electrical plans (permit/inspections by State Board of Electricity)
- Mechanical/Heating, Ventilating, and Air Conditioning (HVAC) with heat loss/gain and ventilation calculations. (requires a separate permit) City of Mankato
- Plumbing (requires a separate permit). State projects-State of Minnesota. Other projects-City of Mankato.
The following documents may be deferred submittals and are required prior to permit issue:
- Special inspections form
- Energy code calculation (building envelope, ventilation, and electrical)
- Hazardous/flammable materials inventory (verify control rooms and H-occupancies)
- State delegation agreements for building and plumbing code for public projects
Additional submittals may become necessary due to the design process:
- Fire suppression with calculations (FD connection, fire pump, and generator on documents)
- Fire alarm (panel location on drawings)
- Contact state health department (food, day care, etc for licensing and plan review)
- Storage racking by structural engineer
- High-piled combustible storage by mechanical engineer
- Liquor license
- Site Plan Review Committee submission
- Land alterations (fill, excavation, erosion and grading in sensitive areas) section 10.82, subdivision 9