Residential Plan Review Requirements

House being built

If you’re building a new home or completing an addition or remodel to your existing home, you need a building permit. The submittals (supporting documents) listed below are required at the time of application.

Please allow a minimum of seven working days for staff to review your application. The process may take longer if submittals are not complete or the project is particularly complex. Work may not begin until the permit is received and on the job site. Starting work without a permit may result in additional fees.

Building permit submittal requirements

Prior to building, you must submit a permit application. Online submission is preferred.
If you prefer paper documents, please submit the following in-person at the Intergovernmental Center, 10 Civic Center Plaza:

  1. Completed building permit application(PDF, 126KB).
  2. A copy of the contractor's license must be on file with the City.
  3. Two copies of the site plan(PDF, 273KB) /survey.
  4. Two complete sets of detailed building plans (one full-size scaled drawing and one 11x17)). Lookout or walkout elevation details must be included. Reverse plans are not accepted.
  5. Energy Code Compliance Certificate and Calculations

Detailed submittals mean faster processing

The more information you provide up front, the more quickly your application can be processed. The following are examples of information you may need to include with your submittals. Depending on project complexity, you may be asked to provide additional information.

Identify which building code is being used. International Residential Code (IRC) or International Building Code (IBC)

Foundation plans must:

  • Provide the reinforcement design table number proposed along with the rod size, spacing (vertical and horizontal), and anchor system for sill plates, or provide an engineered design.
  • Indicate the waterproofing method, drainage system, backfill, dimension from grade to top of foundation wall, and drainage slope away from the foundation wall.
  • Identify the weather barrier product being used. The barrier must qualify as an approved ICC Evaluation Service report product.

Framing structural design information should include:

  • grade/species of lumber
  • type of manufactured materials (joists, beams, columns)
  • dimensions of materials
  • loading bearing points
  • snow live load design (35# minimum)
  • panel and decking materials for diaphragms
  • manufactured trusses
  • special mechanical connection methods and materials
  • rise/run/head clearance
  • any other information necessary to perform a plan review.

Identify decking material. Plastic, composition, and other manufactured products must have an approved ICC Evaluation Service report.

High wall designs exceeding code tables (typically 10 feet) require engineering submittals.

Verify code-compliant wall design method and materials with dimensions and specify narrow wall locations on construction plans (such as garage walls adjacent to overhead garage doors), or provide engineered submittal.

Wall and floor/ceilings: Identify fire test design numbers along with Sound Transmission Class (STC) and Impact Insulation Class (IIC) ratings for wall and floor/ceiling assemblies when applicable.

Foam plastic products (sheet material and spray-applied products) must be identified on plans and comply with flame/smoke ratings, thermal barrier and perm ratings, and must qualify as an ICC Evaluation Service report product or tested product.

Energy/HVAC:

  • Identify which state energy code is being used and provide all supporting data that matches construction plans submitted, including energy code compliance.
  • Provide mechanical code ventilation work sheet for ventilation air, make-up air and combustion air using mechanical code work sheets or approved software programs.
  • Provide heat loss/heat gain calculations for sizing of the furnace and air condition appliances. The balancing report is to be submitted prior to final inspection per applicable mechanical and energy code used.

Duct work: Identify duct material, R-value, vapor barrier, and other special requirements as may be required. (R-8 minimum required in attics and ventilated crawl spaces.)

Roofing: Refer to Asphalt Shingle Roofing and the 2020 Minnesota Residential Code(PDF, 537KB). 

Plumbing permits are a separate application form, fee, and approval.

Mechanical permits are a separate application form, fee, and approval.

Approved job copy package of approved construction documents, inspection card, and permits must be at the job site for all inspections. Inspections may not be performed if the job copy package is not available to the inspector. Work may not continue without approved inspections. Final inspections and a certificate of occupancy are required to occupy a dwelling.

To schedule an inspection, contact staff at 311 or 507-387-8600. Please schedule inspections 24 hours in advance. Inspection requests with less than 24 hours notice will be scheduled on an availability basis.